Traffic Impacts

We apologize in advance for any inconvenience or delays any traffic impacts may cause during construction on this important infrastructure project.  

Please plan ahead and drive according to the road conditions. Stay alert, stay safe, and slow down.

Click the road name under Impact Locations or scroll down for specific project traffic impacts.

Impact Locations

Marine Notification: Credit River Public Water Way

1. Credit River Public Water Way Restriction

Location:

Credit River at the QEW Credit River Bridge

Dates:

Friday November 01, 2024 to Wednesday April 30, 2025

Purpose:

Overhead Construction for the QEW Credit River Twin Bridge

Description:

  • A full closure of the Credit River at the QEW Credit River bridge 

Impact:

  • Construction activities for the bridge foundation
  • Construction of the East-West Pedestrian-Cyclist crossing
  • Major water navigation impacts to rowers, paddlers and public
  • Minor noise impacts are anticipated
  • Work will be weather dependent 

Multi-Use Path

No scheduled disruptions at this time.

QEW

1. Full Ramp Closure

Mississauga Road on-ramp to QEW Eastbound

Location:

QEW Eastbound on-ramp at Mississauga Road

Date/Time:

Monday July 31, 2023 to TBD

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Full closure of the QEW Eastbound on-ramp at Mississauga Road.

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction activities.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

2. Two Lane and Ramp Closures

QEW Westbound & Eastbound between Erin Mills Parkway and Hurontario Street

—UPDATE—

Location:

  • QEW Westbound between Hurontario Street and Erin Mills Parkway
  • QEW Eastbound between Erin Mills Parkway and Hurontario Street
  • QEW Eastbound Off-ramp to South Sheridan Way
  • South Sheridan Way On-ramp to QEW Eastbound

Dates:

Sunday November 17 to Friday December 20, 2024

Times:

10:00PM to 8:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

QEW Westbound Lanes
Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway  
Monday to Thursday Nights
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: Midnight to 5:00AM
Friday Nights
  • Lane 1: Midnight to 7:00AM
  • Lane 2: Midnight to 6:00AM
Saturday Nights
  • Lane 1: 11:00PM to 8:00AM
  • Lane 2: Midnight to 7:00AM
Sunday Nights
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: Midnight to 5:00AM
 
QEW Eastbound Lanes
Two lane closure of QEW Eastbound from Erin Mills Parkway to Hurontario Street
Monday to Thursday Nights
  • Lane 1: 10:00PM to 5:00AM
  • Lane 2: Midnight to 5:00AM
Friday Nights
  • Lane 1: Midnight to 7:00AM
  • Lane 2: Midnight to 6:00AM
Saturday Nights
  • Lane 1: 11:00PM to 8:00AM
  • Lane 2: Midnight to 7:00AM
Sunday Nights
  • Lane 1: 11:00PM to 5:00AM
  • Lane 2: Midnight to 5:00AM
 
QEW Eastbound Off-ramp to South Sheridan Way
Full Closure
  • Midnight to 5:00AM
  • Scheduled Dates: Thursday December 05
 
South Sheridan Way On-ramp to QEW Eastbound
Full Closure
  • Midnight to 5:00AM
  • Scheduled Dates: Thursday December 05

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

3. Two Lane and Ramp Closures

QEW Westbound between Hurontario Street and Erin Mills Parkway. QEW Westbound Off-ramp to Mississauga Road. Mississauga Road On-ramp to QEW Westbound. Hurontario Street On-ramp to QEW Westbound

Location:

  • QEW Westbound between Hurontario Street and Erin Mills Parkway
  • QEW Westbound Off-ramp to Mississauga Road
  • Mississauga Road On-ramp to QEW Westbound 
  • Hurontario Street On-ramp to QEW Westbound

Dates:

Tuesday December 10 to Friday December 20, 2024

Times:

11:00PM to 6:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

QEW Westbound Lanes
Two lane closure from Hurontario Street to Erin Mills Parkway  
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: 11:00PM to 5:00AM
 
QEW Westbound Off-ramp to Mississauga Road
Full Closure
  • Midnight to 5:00AM
 
Mississauga Road On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM
 
Hurontario Street On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction Activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.
  • Signed detour will be set up for off-ramp closures.

Premium Way

1. Single Lane Closure

Premium Way from Stavebank Road to Lynchmere Avenue

Location:

  • Premium Way from Stavebank Road to Lynchmere Avenue

Dates:

Sunday December 01 to Tuesday December 31, 2024

Times:

9:00AM to 3:00PM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Premium Way from Stavebank Road to Lynchmere Avenue
  • Single lane closure
    • 9:00AM to 3:00PM, Monday to Friday
    • Two-way traffic will be maintained at all times under flagging conditions
    • Access to Dickson Road and Lynchmere Avenue will be maintained at all times 
    • No closures on Saturday and Sunday
    • No closures to occur on Tuesday December 24, Wednesday December 25, Thursday December 26 and Friday December 27

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Stavebank Road

No scheduled disruptions at this time.

Dickson Road

No scheduled disruptions at this time.

Hurontario Street

1. Two Lane and Ramp Closures

QEW Westbound between Hurontario Street and Erin Mills Parkway. QEW Westbound Off-ramp to Mississauga Road. Mississauga Road On-ramp to QEW Westbound. Hurontario Street On-ramp to QEW Westbound

Location:

  • QEW Westbound between Hurontario Street and Erin Mills Parkway
  • QEW Westbound Off-ramp to Mississauga Road
  • Mississauga Road On-ramp to QEW Westbound 
  • Hurontario Street On-ramp to QEW Westbound

Dates:

Tuesday December 10 to Friday December 20, 2024

Times:

11:00PM to 6:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

QEW Westbound Lanes
Two lane closure from Hurontario Street to Erin Mills Parkway  
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: 11:00PM to 5:00AM
 
QEW Westbound Off-ramp to Mississauga Road
Full Closure
  • Midnight to 5:00AM
 
Mississauga Road On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM
 
Hurontario Street On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction Activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.
  • Signed detour will be set up for off-ramp closures.

Lynchmere Avenue

No scheduled disruptions at this time.

Mississauga Crescent

No scheduled disruptions at this time.

Mississauga Road

1. Single and Two Lane Closures

Mississauga Road between Kedleston Way and QEW Overpass, South Sheridan Way between QEW Eastbound On-ramp from South Sheridan Way and Mississauga Road

—UPDATE—

Location:

  • Mississauga Road between QEW Overpass to Kedleston Way 
  • South Sheridan Way between the QEW eastbound on-ramp from South Sheridan Way and Mississauga Road

Dates:

Saturday November 23 to Friday December 13, 2024

Times:

8:00PM to 5:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Mississauga Road
One lane closure of Mississauga Road between Kedleston Way to QEW Overpass 
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent will be maintained at all times
 
South Sheridan Way
Two lane nightly closure of South Sheridan Way between the QEW eastbound on-ramp from South Sheridan Way and Mississauga Road
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

2. Single Lane Closures

Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp. South Sheridan Way between South ramp terminal and Mississauga Road

—UPDATE—

Location:

  • Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp
  • South Sheridan Way between South ramp terminal and Mississauga Road

Dates:

Sunday December 01 to Friday December 20, 2024

Times:

8:00PM to 5:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Mississauga Road
One lane closure of Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp 
  • 10:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent will be maintained at all times
 
South Sheridan Way
Two lane closure nightly from South ramp terminal to Mississauga Road
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

3. Two Lane and Ramp Closures

QEW Westbound between Hurontario Street and Erin Mills Parkway. QEW Westbound Off-ramp to Mississauga Road. Mississauga Road On-ramp to QEW Westbound. Hurontario Street On-ramp to QEW Westbound

Location:

  • QEW Westbound between Hurontario Street and Erin Mills Parkway
  • QEW Westbound Off-ramp to Mississauga Road
  • Mississauga Road On-ramp to QEW Westbound 
  • Hurontario Street On-ramp to QEW Westbound

Dates:

Tuesday December 10 to Friday December 20, 2024

Times:

11:00PM to 6:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

QEW Westbound Lanes
Two lane closure from Hurontario Street to Erin Mills Parkway  
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: 11:00PM to 5:00AM
 
QEW Westbound Off-ramp to Mississauga Road
Full Closure
  • Midnight to 5:00AM
 
Mississauga Road On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM
 
Hurontario Street On-ramp to QEW Westbound
Full Closure
  • Midnight to 5:00AM

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction Activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.
  • Signed detour will be set up for off-ramp closures.

North Sheridan Way

No scheduled disruptions at this time.

South Sheridan Way

1. Single and Two Lane Closures

Mississauga Road between Kedleston Way and QEW Overpass, South Sheridan Way between QEW Eastbound On-ramp from South Sheridan Way and Mississauga Road

—UPDATE—

Location:

  • Mississauga Road between QEW Overpass to Kedleston Way 
  • South Sheridan Way between the QEW eastbound on-ramp from South Sheridan Way and Mississauga Road

Dates:

Saturday November 23 to Friday December 13, 2024

Times:

8:00PM to 5:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Mississauga Road
One lane closure of Mississauga Road between Kedleston Way to QEW Overpass 
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent will be maintained at all times
 
South Sheridan Way
Two lane nightly closure of South Sheridan Way between the QEW eastbound on-ramp from South Sheridan Way and Mississauga Road
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

2. Single Lane Closures

Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp. South Sheridan Way between South ramp terminal and Mississauga Road

—UPDATE—

Location:

  • Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp
  • South Sheridan Way between South ramp terminal and Mississauga Road

Dates:

Sunday December 01 to Friday December 20, 2024

Times:

8:00PM to 5:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

Mississauga Road
One lane closure of Mississauga Road between South Sheridan Way and North of QEW Westbound On-ramp 
  • 10:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent will be maintained at all times
 
South Sheridan Way
Two lane closure nightly from South ramp terminal to Mississauga Road
  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

3. Two Lane and Ramp Closures

QEW Westbound & Eastbound between Erin Mills Parkway and Hurontario Street

—UPDATE—

Location:

  • QEW Westbound between Hurontario Street and Erin Mills Parkway
  • QEW Eastbound between Erin Mills Parkway and Hurontario Street
  • QEW Eastbound Off-ramp to South Sheridan Way
  • South Sheridan Way On-ramp to QEW Eastbound

Dates:

Sunday November 17 to Friday December 20, 2024

Times:

10:00PM to 8:00AM

Purpose:

Ongoing QEW Credit River Improvement Project

Description:

QEW Westbound Lanes
Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway  
Monday to Thursday Nights
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: Midnight to 5:00AM
Friday Nights
  • Lane 1: Midnight to 7:00AM
  • Lane 2: Midnight to 6:00AM
Saturday Nights
  • Lane 1: 11:00PM to 8:00AM
  • Lane 2: Midnight to 7:00AM
Sunday Nights
  • Lane 1: 11:00PM to 6:00AM
  • Lane 2: Midnight to 5:00AM
 
QEW Eastbound Lanes
Two lane closure of QEW Eastbound from Erin Mills Parkway to Hurontario Street
Monday to Thursday Nights
  • Lane 1: 10:00PM to 5:00AM
  • Lane 2: Midnight to 5:00AM
Friday Nights
  • Lane 1: Midnight to 7:00AM
  • Lane 2: Midnight to 6:00AM
Saturday Nights
  • Lane 1: 11:00PM to 8:00AM
  • Lane 2: Midnight to 7:00AM
Sunday Nights
  • Lane 1: 11:00PM to 5:00AM
  • Lane 2: Midnight to 5:00AM
 
QEW Eastbound Off-ramp to South Sheridan Way
Full Closure
  • Midnight to 5:00AM
  • Scheduled Dates: Thursday December 05
 
South Sheridan Way On-ramp to QEW Eastbound
Full Closure
  • Midnight to 5:00AM
  • Scheduled Dates: Thursday December 05

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Kedleston Way

No scheduled disruptions at this time.

Knareswood Drive

No scheduled disruptions at this time.

Erin Mills

No scheduled disruptions at this time.