Traffic Impacts

We apologize in advance for any inconvenience or delays any traffic impacts may cause during construction on this important infrastructure project.  

Please plan ahead and drive according to the road conditions. Stay alert, stay safe, and slow down.

Click the road name under Impact Locations or scroll down for specific project traffic impacts.

Impact Locations

Marine Notification: Credit River Public Water Way

No scheduled disruptions at this time.

Multi-Use Path

No scheduled disruptions at this time.

QEW

1. Two Lane Closures and Ramp Closures

QEW Westbound between Hurontario Street and Erin Mills Parkway. QEW Eastbound between Winston Churchill Boulevard and Hurontario Street. QEW Eastbound On-ramp from Erin Mills Parkway. QEW Eastbound Off-ramp to South Sheridan Way.

—UPDATE—

Location:

  1. QEW Westbound between Hurontario Street and Erin Mills Parkway
  2. QEW Eastbound between Winston Churchill Boulevard and Hurontario Street
  3. QEW Eastbound On-ramp from Erin Mills Parkway
  4. QEW Eastbound Off-ramp to South Sheridan Way

Dates: Wednesday November 26 to Friday December 19

Times: 10:00PM to 8:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. QEW Westbound Lanes

Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway 

Monday – Thursday Nights

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

2. QEW Eastbound Lanes

Two lane closure of QEW Eastbound from Winston Churchill Boulevard to Hurontario Street  

Monday – Thursday Nights

  • One Lane: 10:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

3. QEW Eastbound On-ramp from Erin Mills Parkway

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Monday December 08

4. QEW Eastbound Off-ramp to South Sheridan Way

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Friday December 12

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.

Premium Way

1. Single Lane Closure

Premium Way between Stavebank Road and Lynchmere Avenue

Location:

  • Premium Way from Stavebank Road to Lynchmere Avenue

Dates: Monday December 01 to Friday December 19

Times: 9:00AM to 3:00PM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

Premium Way

One lane closure of Premium Way from Stavebank Road to Lynchmere Avenue (Monday to Friday)

  • 9:00AM to 3:00PM
  • Two-way traffic will be always maintained under flagging conditions
  • Access to Dickson Road and Lynchmere Avenue will be always maintained
  • No closures on Saturday and Sundays

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Stavebank Road

1. Single Lane Closure

Premium Way between Stavebank Road and Lynchmere Avenue

Location:

  • Premium Way from Stavebank Road to Lynchmere Avenue

Dates: Monday December 01 to Friday December 19

Times: 9:00AM to 3:00PM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

Premium Way

One lane closure of Premium Way from Stavebank Road to Lynchmere Avenue (Monday to Friday)

  • 9:00AM to 3:00PM
  • Two-way traffic will be always maintained under flagging conditions
  • Access to Dickson Road and Lynchmere Avenue will be always maintained
  • No closures on Saturday and Sundays

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Dickson Road

1. Single Lane Closure

Premium Way between Stavebank Road and Lynchmere Avenue

Location:

  • Premium Way from Stavebank Road to Lynchmere Avenue

Dates: Monday December 01 to Friday December 19

Times: 9:00AM to 3:00PM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

Premium Way

One lane closure of Premium Way from Stavebank Road to Lynchmere Avenue (Monday to Friday)

  • 9:00AM to 3:00PM
  • Two-way traffic will be always maintained under flagging conditions
  • Access to Dickson Road and Lynchmere Avenue will be always maintained
  • No closures on Saturday and Sundays

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Hurontario Street

1. Two Lane Closures

QEW Westbound & Eastbound between Erin Mills Parkway and Hurontario Street.

—UPDATE—

Location:

  1. QEW Westbound between Hurontario Street and Erin Mills Parkway
  2. QEW Eastbound between Erin Mills Parkway and Hurontario Street
  3. QEW Westbound On-ramp from Hurontario Street
  4. QEW Westbound On-ramp from Mississauga Road

Dates: Wednesday November 26 to Friday December 19

Times: 10:00PM to 8:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. QEW Westbound Lanes

Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway 

Monday – Thursday Nights

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

 

2. QEW Eastbound Lanes

Two lane closure of QEW Eastbound from Erin Mill Parkway to Hurontario Street  

Monday – Thursday Nights

  • One Lane: 10:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

 

3. QEW Westbound On-ramp from Hurontario Street

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Wednesday December 03

 

4. QEW Westbound On-ramp from Mississauga Road

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Monday December 01 and Tuesday December 02

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.
  • Signed detour will be set up for off-ramp closures.

Lynchmere Avenue

1. Single Lane Closure

Premium Way between Stavebank Road and Lynchmere Avenue

Location:

  • Premium Way from Stavebank Road to Lynchmere Avenue

Dates: Monday December 01 to Friday December 19

Times: 9:00AM to 3:00PM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

Premium Way

One lane closure of Premium Way from Stavebank Road to Lynchmere Avenue (Monday to Friday)

  • 9:00AM to 3:00PM
  • Two-way traffic will be always maintained under flagging conditions
  • Access to Dickson Road and Lynchmere Avenue will be always maintained
  • No closures on Saturday and Sundays

Impact:

  • Traffic Disruptions are anticipated.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the date listed above.

Mississauga Crescent

No Scheduled Disruptions at this time

Mississauga Road

1. One Lane and Two-Lane Nightly Closure

Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road. South Sheridan Way between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way.

—UPDATE—

Location:

  1. Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road.
  2. South Sheridan Way between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way.

Dates: Wednesday November 26 to Friday December 19

Times: 8:00PM to 5:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. Mississauga Road

One lane nightly closure of Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road

  • 10:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent and Kedleston Way will be maintained at all times

2. South Sheridan Way

Two lane nightly closure between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way

  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • No Closures to occur on weekends
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.

North Sheridan Way

No scheduled disruptions at this time.

South Sheridan Way

1. One Lane and Two-Lane Nightly Closure

Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road. South Sheridan Way between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way.

—UPDATE—

Location:

  1. Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road.
  2. South Sheridan Way between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way.

Dates: Wednesday November 26 to Friday December 19

Times: 8:00PM to 5:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. Mississauga Road

One lane nightly closure of Mississauga Road between Kedleston Way and QEW Westbound On-ramp at Mississauga Road

  • 10:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions
  • Access to/from Mississauga Crescent and Kedleston Way will be maintained at all times

2. South Sheridan Way

Two lane nightly closure between Mississauga Road and QEW Eastbound On-ramp at South Sheridan Way

  • 8:00PM to 5:00AM
  • Two-way traffic will be maintained at all times under flagging conditions

Impact:

  • Traffic Disruptions are anticipated.
  • No Closures to occur on weekends
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.

2. Two-Lane Nightly Closure

South Sheridan Way between the QEW Eastbound On and Off-ramps at South Sheridan Way to West of Indian Grove.

—UPDATE—

Location:

  1. South Sheridan Way between the QEW Eastbound On and Off ramps at South Sheridan Way to West of Indian Grove

Dates: Friday November 21 to Friday December 19

Times: 8:00PM to 5:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. South Sheridan Way

Two lane nightly closure of South Sheridan Way between the QEW Eastbound On and Off ramps at South Sheridan Way to West of Indian Grove

  • 8:00PM to 5:00AM
  • Two-way traffic will be always maintained under flagging conditions
  • No closure to occur on weekends
  • Access to the QEW Eastbound on and of ramps will always be maintained

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.

3. Two Lane Closures and Ramp Closures

QEW Westbound between Hurontario Street and Erin Mills Parkway. QEW Eastbound between Winston Churchill Boulevard and Hurontario Street. QEW Eastbound On-ramp from Erin Mills Parkway. QEW Eastbound Off-ramp to South Sheridan Way.

—UPDATE—

Location:

  1. QEW Westbound between Hurontario Street and Erin Mills Parkway
  2. QEW Eastbound between Winston Churchill Boulevard and Hurontario Street
  3. QEW Eastbound On-ramp from Erin Mills Parkway
  4. QEW Eastbound Off-ramp to South Sheridan Way

Dates: Wednesday November 26 to Friday December 19

Times: 10:00PM to 8:00AM

Purpose: Ongoing QEW Credit River Improvement Project

Description:

1. QEW Westbound Lanes

Two lane closure of QEW Westbound from Hurontario Street to Erin Mills Parkway 

Monday – Thursday Nights

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 6:00AM
  • Two Lanes: Midnight to 5:00AM

 

2. QEW Eastbound Lanes

Two lane closure of QEW Eastbound from Winston Churchill Boulevard to Hurontario Street  

Monday – Thursday Nights

  • One Lane: 10:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

Friday Night

  • One Lane: Midnight to 7:00AM
  • Two Lanes: Midnight to 6:00AM

Saturday Night

  • One Lane: 11:00PM to 8:00AM
  • Two Lanes: Midnight to 7:00AM

Sunday Night

  • One Lane: 11:00PM to 5:00AM
  • Two Lanes: Midnight to 5:00AM

 

3. QEW Eastbound On-ramp from Erin Mills Parkway

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Monday December 08

 

4. QEW Eastbound Off-ramp to South Sheridan Way

Full Closure

  • Midnight to 5:00AM
  • Scheduled Dates: Thursday December 04

Impact:

  • Traffic Disruptions are anticipated.
  • Overnight Construction activities may produce noise.
  • All closures are weather dependent.
  • Closure dates are subject to change and may not take place on all the dates listed above.

Kedleston Way

No scheduled disruptions at this time.

Knareswood Drive

No scheduled disruptions at this time.

Erin Mills

No scheduled disruptions at this time.